The City of Bakersfield issued 372 residential swimming pool permits in the monthly reports we could read, covering January 2025 through September 2026. The December 2025 report was not available. That works out to roughly 18 new pools a month inside city limits alone, not counting Kern County, Shafter, Wasco, Delano, Taft or Tehachapi, which permit their own.
Method
Each month the city posts a "Daily Report" PDF listing every permit issued, with the permit number, date, use code, address, contractor and declared valuation. We read the twenty reports from January 2025 through September 2026, kept only permits in the residential swimming pool category, and removed duplicates where a permit appeared in more than one report. Rows that the PDF split across lines in a way we could not reconstruct with confidence were left out of the detailed counts below. We do not publish addresses or contractor names, so this page shows only totals.
Permits by month
Source: City of Bakersfield monthly Daily Report permit listings. Bars show residential pool permits issued per month.
| Month | 2025 | 2026 |
|---|---|---|
| Jan | 16 | 15 |
| Feb | 19 | 8 |
| Mar | 14 | 20 |
| Apr | 22 | 29 |
| May | 34 | 34 |
| Jun | 28 | 14 |
| Jul | 8 | 27 |
| Aug | 23 | 22 |
| Sep | 9 | 11 |
| Oct | 22 | n/a |
| Nov | 19 | n/a |
| Dec | n/a | n/a |
May was the busiest month in both years, with 34 permits each time, and April was close behind. That pattern follows the calendar of heat. Families decide in winter, design in early spring, and file in April and May so the pool is filled before July. The quieter months are scattered: July and September 2025 and February 2026 each fell to single digits.
What it means for you. If you want to swim by late spring, file before the rush. A permit submitted in January or February competes with fewer projects at plan review and with fewer jobs on each builder's calendar. If you can wait until late summer or fall, you may find builders with shorter backlogs.
Pool or pool and spa
Each permit carries a use code. Of the 372 permits:
- 239 (64%) were coded as a swimming pool alone.
- 122 (33%) were coded as a pool with an attached spa.
- 3 were spa-only permits, and 8 carried other or unclear codes.
So about one Bakersfield pool in three is built with a spa from the start. A spa is far cheaper to include during construction than to add later, because it shares the excavation, plumbing trench, heater and equipment pad. See pool and spa combinations for designs and costs.
Declared values
Declared valuation as written on each permit. Gold bar: placeholder or partial values under $20,000.
Builders declare a valuation when they apply. 135 permits (36%) list less than $20,000. Most of those use a standard figure of about $12,000 to $15,000, which reflects only part of the work, so we leave them out of the price analysis.
Among the 237 permits with a valuation of $20,000 or more:
- The median was about $50,000.
- The middle half ran from about $40,000 to $69,000.
- One in ten was above about $81,000, and 13 were over $100,000.
How to read this. Declared values usually cover the pool structure and core work, not always the full deck, fencing, landscaping, outdoor kitchen or every upgrade. Final contract prices for a complete backyard commonly run higher, which is why our cost guide and estimator show ranges above these medians. If a bid comes in far below the permit medians for a full project, ask what is missing.
Who builds Bakersfield's pools
About 70 different contractor names appear across the 372 permits. The market is concentrated at the top and long at the tail:
- The single busiest builder filed 84 permits, close to a quarter of the total.
- The five busiest together filed 191, just over half.
- 48 names appear only once or twice.
We do not rank or name builders here. Volume reflects marketing and capacity, not workmanship. A builder with many recent permits does give you plenty of nearby, inspected pools to look at, while a smaller firm may offer more owner involvement and an earlier start date. Whichever you choose, check the license on the Contractors State License Board site and ask for addresses of recent local pools.
Where the pools are
Most permit rows in the reports omit a ZIP code, so this is a partial view. Among the rows that include one, southwest Bakersfield led: 93311 (17) and 93313 (11), followed by 93314 (9) and 93306 (8) on the northeast side. The pattern matches the city's newer tracts, where lots are large enough for a pool and many homes were built without one. See our service areas for neighborhood detail.
Almost all retrofits
Only a handful of the permits were filed by homebuilders as part of new home construction. Nearly every Bakersfield pool in this period was added to a house someone already lived in. That makes access, existing utilities and side-yard width the defining issues of a local pool project, which is why our construction timeline and permit guide focus on them.
Using this data
You are welcome to cite these figures with a link to this page. The underlying monthly reports are public records published by the City of Bakersfield. Permits in unincorporated Kern County and in other Kern cities are issued by those agencies and are not included here.
A planning calendar built from the data
Working backward from the May permit peak gives a practical timeline for a pool you want to swim in by early summer:
| When | What to do | Why |
|---|---|---|
| October to December | Collect ideas, set a budget, check HOA rules | Builders have time for design visits |
| January | Meet two or three builders and compare written bids | Permit volume is still moderate |
| February | Sign, finalize the design, submit plans | You are ahead of the spring rush |
| March to April | Plan check, then dig, steel and gunite | Mild weather suits concrete work |
| May to June | Tile, deck, equipment, finish and start-up | Water in before the first 100-degree days |
If you start after April, plan for a mid-summer or later finish. A late-summer or fall start is a good option if you would rather avoid the busiest months.